Ibri II 500MW Solar PV Independent Power Plant Project

  • Home
  • Projects
  • Ibri II 500MW Solar PV Independent Power Plant Project

Ibri II 500MW Solar PV Independent Power Plant Project

The Ibri II Solar PV Independent Power Plant Project (the Project) is a 500 mega-watt greenfield solar photovoltaics power plant in Ibri
The Overview!

Ibri II 500MW Solar PV Power Plant Project

Roughly 300 kilometers west of Muscat just off the Buraimi–Ibri Highway, the largest utility-scale solar park in Oman is nearing completion. Extending over 13 million square meters and containing about 1.4 million solar panels, the solar park will provide renewable energy for about 33,000 homes once completed and avoid the emission of approximately 800,000 tons of CO₂-equivalent per year, contributing to achieving Oman’s nationally determined contribution under the Paris Agreement.Our high-efficiency PV cells are suitable for a broad range of module applications including private rooftop installations, commercial and industrial rooftop installations, remote power generators and large-scale power plants on the ground and on the water.

Ibri II Solar IPP: The 500 MW Solar PV project (Ibri II Solar IPP) began commercial operation in July 2021. It is owned and operated by Shams Ad Dhahira Generating Company under a PPA with OPWP. The project is configured with single-axis tracking and bi-facial PV panels.

500 MW

Buraimi–Ibri 

Inaugurated in January 2022

Solar PV – Tracking

Shams Ad-Dhahirah Generating Co. (SAOC)

Power

570 MWp

Investment

$ 14,600

Yearly Output

1,598 GWh

Electricity To Power

33,000 Homes

Reduced  Emissions

340,000    t. of CO2

The Objective

Ibri II 500MW Solar PV

The objectives of the Project are to:

(a) increase the availability of the renewable power generation capacity and improve the balance between supply and demand during the peak hours in Oman’s Main Interconnected System grid which serves Muscat and northern Oman.

(b) reduce the dependence on gas and other fossil fuels for electricity generation and move to a more balanced and environmentally sustainable energy mix.

Highlights

Ibri II Solar IPP

The 500 MW Solar PV project began commercial operation in August 2021. It is owned and operated by Shams Ad Dhahira Generating Company under a PPA with PWP. The project is configured with single-axis tracking and bi-facial PV panels.

The N-type high-efficiency bi-facial cells and modules installed across the sprawling site are deemed ideal for Oman's environmental conditions. At peak generation capacity, the plant will produce enough carbon-free electricity to power an estimated 33,000 homes, while also offsetting offset 340,000 tonnes of carbon dioxide emissions a year.
Description!

History

The Ibri II Solar PV Independent Power Plant Project (the Project) is a 500 mega-watt greenfield solar photovoltaics power plant in Ibri, Oman which is being developed by Shams Ad-Dhahira Generating Company SAOC (the Borrower), a special purpose vehicle incorporated under the laws of Oman.

Oman Power and Water Procurement Co (OPWP) awarded the Project to the consortium led by International Company for Water and Power Projects (ACWA Power) following a detailed financial, technical and legal evaluation of bid proposals received through international competitive tender. The Project is implemented under Build, Own and Operate model under a bilateral arrangement of offtake by OPWP for 15 years from the Scheduled Commercial Operation Date on June 1, 2021. The Power Purchase Agreement was signed between OPWP and the Borrower on April 30, 2019. 

Can we meet the growing demand for electricity & protecting our climate?

Vision Oman 2040!

Solar In Oman Energy Mix

A leading international supplier of solar wafers for PV module manufacturers. We market a complete portfolio of reliable, high-quality solar wafers to meet the manufacturing demands of our customers. Our solar silicon wafers can be built to the exact specifications of solar manufacturers.

Working with our suppliers and trade associations like SEIA we help PV manufacturers increase efficiency while minimizing costs.

1
Projects Completed
In Last 5 Years
1
Qualified Employees
& Workers With Us